Once the excavation got going the dirt had to go somewhere. The garden became a causality. We wouldn't have had time to do any gardening this year anyway.
Brescia sitting on top of a few days of digging. 03/12/14


The first temp wall on the first permanent footings where the cellar was.

Preparing for the first wall pour. There is a lot of rebar to hold things together.

A temporary beam holding up the middle of the house floor.

04/23/14
More footings formed up

3-19 Pouring the footings


3-19 concrete poured

3-19 footings, notice the gaps for future plumbing.


3-19 poured footings for the new master bath

3-20 foundation walls for master bath ready for concrete

3-20 first basement exterior walls framed and ready to be filled